Blue Peaks Roofing re-roofed the Akron School District R-1 PK-12 campus in Akron, Colorado, after hail damage. We tore off the original standing seam roof and installed nearly 988 squares of new standing seam metal and TPO between late May and mid-August 2026, so staff and students came back to a finished roof.

A school roof has to be finished before the school year starts. This campus needed nearly 988 squares of new roof across two different systems, with clean transitions between the metal and the low-slope TPO, on a rural eastern plains site exposed to Colorado weather.
Rooftop mechanical, electrical and gutter work all had to be sequenced around the roofing so the whole campus was ready on time.
Learn more about our standing seam metal roofing and commercial TPO roofing.
Material was staged and offloaded by crane during mobilization week. The work area was fenced, crews used a boom lift for elevated access and tied off on the metal, and debris was controlled throughout the job.
Our crews documented the work from tear-off to closeout with more than 7,000 CompanyCam photos, so the district had a clear record of every phase.
Before, during and after photos from the Akron campus, from the original roof to the finished metal and TPO.












See more commercial roofing projects, our South Adams County Fire stations re-roof, or our commercial roofing services.
Request a roof assessment and a written proposal your board can review. Call (303) 808-0687 or send us a note through our contact page.